Project Sequence Plan

 

The Triton Knoll Electrical System (TKES) Project Sequence Plan (PSP) has now been submitted to Local Authorities and has been distributed to agreed stakeholders.

The PSP is a key document in the management of the project’s onshore construction programme.

The PSP has been developed in accordance with Requirement 5(11) of the TKES Development Consent Order and details the indicative sequencing of the onshore cable works, including landfall works. The plan is required to be submitted to the relevant Planning Authorities at least three months prior to the commencement of the first stage of the onshore cable works. The plan will be updated when significant changes are made and provided to the relevant Planning Authorities, communicated to key stakeholders and updated on our website.