Project Diary

This section is designed to help you remain aware of the anticipated major timescales and milestones for the development, construction and operation of the wind farm.

Please bear in mind, that these timings may change as the project develops.

2017

  • Detailed design and mitigation works, including drainage design and discussions on cropping schedule etc. These works will feed into the final project design.
  • Consultation on and agreement of management plans which are required to be approved by the Local Planning Authorities.
  • Community drop-in sessions to be arranged to further explain and discuss design and construction.
  • Organisation and start-up of the ‘Local Liaison Committee’.

2016

  • Examination of the Triton Knoll electrical system ended
  • Development Consent Order awarded by the Secretary of State for Business, Energy and Industrial Strategy for the Electrical System
  • Onshore and offshore site investigation works taking place
  • Independent agricultural liaison, soil and drainage specialists brought on board to work with landowners

2015

  • Statkraft sign agreement with RWE Innogy to jointly develop Triton Knoll.
  • Submission of a consent application for the electrical system components of the offshore wind farm.
  • Site Investigation campaign undertaken at offshore array site.

2014

  • Update on location of the onshore electrical infrastructure.
  • Consultation with statutory bodies, landowners and communities on the electrical system.
  • Formal consultation with statutory bodies, landowners and communities on the electrical system under the Planning Act (2008).

2013

  • Electrical technology choice and locations of offshore and onshore cable route, onshore substation and any additional infrastructure is confirmed.
  • Consultation with stakeholders on the alternative options for the location of the onshore elements of the project.
  • Development consent awarded by the Secretary of State for Energy and Climate Change for the offshore array.
  • Secretary of State directs that the electrical system application can be submitted to the planning inspectorate.
  • Change in capacity range of the project to up to 900MW.

2012

  • National Grid issue an offer to connect Triton Knoll offshore wind farm to the existing electricity transmission network at a substation at Bicker Fen.
  • offshore wind farm consent application submitted to the Infrastructure Planning commission and accepted for examination.
  • Environmental, engineering and technical studies commence on the options for the electrical system infrastructure to understand what it will comprise and to identify sites and routes for the infrastructure.

2011

  • Formal consultation on the offshore wind farm component of the project.
  • Alterations were made to the wind farm project based on the results of the studies and consultation undertaken. For example, the maximum number of offshore wind turbines was reduced from 333 to 288 in light of comments from nature conservation bodies and to mitigate potential impacts on birds. Review of options with National Grid for the onshore connection location for the project.
  • Conclusion to the strategic options review undertaken with National Grid, new location to connect to the grid has been confirmed at Bicker Fen, south west of Boston, Lincolnshire.

2010

  • Consultation on onshore substation options.
  • Informed by National Grid that they were to undertake a new review of options for the onshore connection. Given the significant amount of time that it was anticipated to take to carry out this review, it was decided that Triton Knoll offshore wind farm would be progressed as two separate packages; the offshore wind farm itself and the electrical system.

2008 - 2009

  • Offshore and onshore environmental surveys.