Project’s ‘healthy’ safety record unlocks cash boost for Grimsby foodbank

Donations recognise over 2 million hours of safe working(1) by project team Charity says business support is vital as demand for services rockets. A top safety record at Triton Knoll Offshore Wind Farm is helping a local Grimsby foodbank during what is proving to be one of their toughest times. The nationally significant infrastructure project … Read more

Major milestone as Triton Knoll’s electricity infrastructure takes shape offshore

Triton Knoll has marked another significant milestone in the delivery of critical new UK energy infrastructure, with the safe installation of the first of two offshore substation platforms (OSPs). At 1400 tonnes each, these platforms will operate at the heart of the offshore wind farm which, when fully operational will be capable of generating enough … Read more

Meet the team managing construction of Triton Knoll 32 km offshore

SOV team Grimsby

Floating home for Triton Knoll’s UK offshore construction team makes port at Grimsby Two-weeks rotation will generate activity for local services as teams of 45 swap places. Meet the UK construction management team living and working offshore around the clock, to build the state-of-the-art Triton Knoll Offshore Wind Farm project. The team is permanently based … Read more

Community projects share £102,000 January windfall from Triton Knoll

  -Fund has so far allocated over £340,000 to 39 community projects -Fourth funding round is now open for bids -Annual Community Fund will take over from 2021. Thirteen local community initiatives and projects are the latest to successfully bid into the Triton Knoll Community Fund and will share a windfall of £101,670. To date, … Read more

First foundation installed at Triton Knoll Offshore Wind Farm

Triton Knoll is delighted to confirm that the first of our 90 wind turbine monopile foundations has been safely and successfully installed, 32km off the Lincolnshire coast. The c.600 tonne steel monopile and its bright yellow transition piece was installed by Seaway7’s ‘Strashnov’ which is contracted to transport and install all 90 of the wind … Read more

Triton Knoll heads into 2020 with start of offshore construction

New Grimsby team will manage all offshore construction activity Foundations will be the first components to be installed offshore. Triton Knoll celebrates the new year with a major milestone as it aims to begin installation of the first state-of-the-art offshore components at the most powerful windfarm in the innogy (1) fleet. During 2020, the project … Read more

Foundations taking shape ready for offshore substations

  Exciting progress continues to be achieved with the assembly of our two offshore substation platforms (OSP). The first of two transition piece (TP) bottom sections has now been up-ended at Smulders’ Wallsend yard near Newcastle, ready for the next steps in the production process. The large, yellow OSP East TP in our latest film … Read more